Construction of third house for orphans in Zarya to start in second quarter of 2018

12:12 | 08.01.2018 | Society

Print

Penza, 8 January 2018. PenzaNews. The construction of the third house for orphans in Penza Zarya will start in the second quarter of 2018. This was reported by the head of the Capital Construction Department of Penza Igor Umnov.

Construction of third house for orphans in Zarya to start in second quarter of 2018

© PenzaNewsBuy the photo

During the visit to the site on Monday, January 8, he explained to the head of the Penza administration Victor Kuvaytsev that the construction will begin after the expertise on a technical part is received.

The mayor noted that the construction of the first and second buildings should be carried out without interruptions to ensure that the facilities are commissioned within the deadlines set by the contract.

"We have everything we need for this – both building materials and workforce," Victor Kuvaytsev said.

As it was reported by the press service of the Penza administration, in Zarya walls of the first building are constructed, floor slabs are installed on the fourth floor. Installation of the upper part of the foundation is carried out on the site of the second house.

23 people are involved in the construction. Work is carried out in one shift without days off.

Under the terms of the contract, the first building must be finished in June 2018, the second one – in September. The construction of the third building must be finished in March 2019.